CONSTRUCTION OF THE TRACK SUPERSTRUCTURE OF THE THESSALONIKI – IDOMENI DEVIATION ON THE POLYKASTRO – IDOMENI SECTION FROM CH. 53+000 TO CH. 73+000, TRACK SUPERSTRUCTURE OF POLYKASTRO RAILWAY STATION, ELECTRIFICATION WORKS, REMOTE CONTROL OF ELECTRIFICATION ON THE NEW DEVIATION AND LINE FENCING

Project in progressSignalling / remote control
PhaseIn progress
Line / AxisTHESSALONIKI – IDOMENI
Area / RegionThessaloniki
Section / Chainage53+000
Length20 km
Start date39918
FundingNSRF 2007-2013 CEF 2014-2020 NATIONAL RESOURCES
Project cost13,916,980.61 €
Contractor / contractTERNA ENERGY S.A.

Description

The project concerns the laying of the track superstructure at the New Polykastro Railway Station and its connection with the existing line towards the Existing Polykastro Railway Station, as well as the study, supply, delivery, construction and installation, trial operation and delivery in operation of the electrification system with remote control of the single railway line. Compliance of the network with the principles of interoperability is achieved.