CONSTRUCTION OF THE SUPERSTRUCTURE, STATIONS AND HALTS, INSTALLATION OF SIGNALLING, TELECOMMUNICATIONS, ELECTRIFICATION AND E/M INSTALLATIONS OF THE PANAGOPOULA TUNNEL ON THE RODODAFNI - RIO SECTION

Project in progressSignalling / remote control
PhaseIn progress
Line / AxisRODODAFNI - BOZAITIKA (RIO AREA)
Area / RegionPeloponnese
Length28.8 km
Start date44887
FundingYMEPERAA 2014-2020
Project cost125,763,774.57 €
Contractor / contractJV TERNA S.A. - MYTILINEOS S.A.

Description

Works for the completion of the Rododafni - Rio section, 28.8 km in length. 1. The construction of the superstructure of 28.8 km of double railway track, with slab track in the two bores of the Panagopoula tunnel, 4.5 km each, and ballasted track on the remainder of the section. 2. The construction of seven (7) railway halts/stations 3. The electromechanical installations 4. The construction of the electrification with remote control and the connection to the Aigio traction substation. 5. The installation of a bidirectional signalling system with remote control, telecommunications and ETCS Level 1. 6. Other works such as the installation of noise barriers, landscaping works and track safety works.