Greece is travelling by train again. · Live Train Tracking at railway.gov.gr

PhaseIn progress
Line / AxisIsthmus – Loutraki
Area / RegionPeloponnese
Length6.4 km
Start date43620
FundingYMEPERAA 2014-2020
Project cost6,391,258.24 €
Contractor / contractMYTILINEOS – XANTHAKIS JOINT VENTURE
Description
The purpose of the project is the conversion of the existing single metre-gauge Isthmus – Loutraki line into a standard-gauge line 6.4 km in length, with signalling and electrification, and its final connection, in the area of the Isthmus, with the existing High-Speed Railway Line (HSRL) of the Suburban Railway operating between Kiato – Corinth – Airport.
Projects in progress
All projects
Project in progressSignalling / remote control
CONSTRUCTION OF THE SUPERSTRUCTURE, STATIONS AND HALTS, INSTALLATION OF SIGNALLING, TELECOMMUNICATIONS, ELECTRIFICATION AND E/M INSTALLATIONS OF THE PANAGOPOULA TUNNEL ON THE RODODAFNI - RIO SECTION

Project in progressElectrification
CONSTRUCTION OF AN ELECTRIFICATION SYSTEM AND NOISE BARRIERS ON THE KIATO – RODODAFNI SECTION

Project in progressLine infrastructure
UNDERGROUNDING OF THE LINE IN THE SEPOLIA AREA

Project in progressStations